Coil Handling & Compacting Machine
Required Redesign & Reconfiguration

When a major US machine manufacturer experienced a challenge at its China wire drawing mill from a malfunctioning coil compacting system, the engineers at The Hope Group responded with a machine assessment that led to a redesign and reconfiguration to bring the equipment into its original design specifications.

The coil handling and compacting machine, which compresses large coils of wire and then secures them with either wire binding or steel strapping, was not working correctly. The machine had developed an inconsistent compacting force and coil positioning. In describing the problem, the chief engineer at The Hope Group described the problem as "the 'hands' of the compactor would come together to squeeze the coil, but the force of the one 'hand' would push the other out of position."

Client engineers and the engineering team at The Hope Group worked together designing needed changes to the hydraulic control system used on the compactor. Both sides of the compactor would come together to squeeze the coil, but the force of one side would periodically push the other out of position. Additionally, force control was erratic due to inconsistent pressure control. Both issues combined to produce coils with inconsistent compaction and resultant potential damage to the coil.

Inconsistent Positioning

After analyzing the circuit and the power unit, the first issue of inconsistent positioning was determined to be a result of using large DIN cartridge valves, whose performance is susceptible to dirt and debris in the system. To match the filtration level of the hydraulic power unit, the team chose low leakage poppet style pilot operated check valves to replace the DIN valves. In order to meet the expected flow rate requirements two poppet PO checks were installed in parallel for each DIN valve.

Inconsistent Pressure Control

The issue of inconsistent pressure control was found to be caused by over pressurization of the system during initial cylinder approach. Specifically, the cylinders were run in regeneration mode for the initial approach and dropped out of regeneration mode for final compaction. However, due to system resistance the pressure required for regeneration mode was greater than that required for final compaction. Because control of pressure was being accomplished by a proportional pressure relief valve – lowering the pressure set point at the time of compaction resulted in periods of instability as the valve attempted to lower the system pressure to the desired level – adversely affecting compaction force.

Solution Achieved

The solution was achieved with the replacement of the existing valves with faster, larger Parker proportional directional and relief valves, along with a wholesale redesign of the manifold, simplification of the hydraulic circuitry, and enlargement of associated piping and hoses, which resulted in lowering regeneration system pressure to levels well below compaction pressure, greatly improving compaction reliability. Once the redesign was completed, the hydraulic control system was assembled, tested and packed for shipment to Shanghai, China.



top

 
wire-drawing-mill
A newly-built coil compacting system being installed in China was malfunctioning. The engineers at The Hope Group were contacted based on their experience and knowledge of hydraulic control systems used in the wire drawing industry. The solution included changes in valves, a simplified electrical circuit and a filtration solution.


horizontal-compactor
Horizontal Compactor

vertical-compactor
Vertical Compactor
 
Technical-Support
get-assistance
request-a-quote
order-hope-direct
ask-an-engineer
ask-betsey-508-393-7660
ask-the-owner
view-line-cards
request-a-catalog
view-cad-drawings
hose-finder-app

Our-Best-Advice
kevin-mcknerney   Conduit Energy Recovery Helps Westfield MA Pipeline Project
Kevin McKnerney
Hydraulic Specialist

Benji-Grubel   Are You Keeping the Application in Mind When Selecting Your Hydraulic Hose?
Dave Maloney
Project Engineer

Peter-Rhoten   Oil and Water Are Not Your Friend
Peter Rhoten
Hope Air Systems

Donna-Tibbetts   One of Our Stores is Open 24 Hours a Day!
Donna Tibbetts
Operations & Service Mgr

doug-markham-ipower-new-england   When Should Materials be Stocked at Point of Use?
Doug Markham
President, iPower NE

 
 
 
   
thg-logo

THG Corporation
70 Bearfoot Road
Northborough, MA 01532

Phone: 508-393-7660 | Fax: 508-393-8203 | Email

Terms & ConditionsLegal DisclaimerJobsOur Mission

© 2015, THG Corporation. All rights reserved