the-hope-group-homeabout-the-hope-groupnwes-from-the-hope-groupsite-mapcontact-the-hope-groupcustomer-login

Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player

Product Lines  -  System Solutions  -  Markets Served  -  More Solutions
Wire Drawing Mill
wire-drawing-mill

A newly-built coil compacting system being installed in China was malfunctioning. The engineers at The Hope Group were contacted based on their experience and knowledge of hydraulic control systems used in the wire drawing industry. The solution included changes in valves, a simplified electrical circuit and a filtration solution.



Coil Handling & Compacting Machine
Required a Redesign & Reconfiguration

When a major US machine manufacturer experienced a challenge at its China wire drawing mill from a malfunctioning coil compacting system, the engineers at The Hope Group responded with a machine assessment that led to a redesign and reconfiguration to bring the equipment into its original design specifications.

The coil handling and compacting machine, which compresses large coils of wire and then secures them with either wire binding or steel strapping, was not working correctly. The machine had developed an inconsistent compacting force and coil positioning. In describing the problem, the chief engineer at The Hope Group described the problem as "the 'hands' of the compactor would come together to squeeze the coil, but the force of the one 'hand' would push the other out of position."

Client engineers and the engineering team at The Hope Group worked together designing needed changes to the hydraulic control system used on the compactor. Both sides of the compactor would come together to squeeze the coil, but the force of one side would periodically push the other out of position. Additionally, force control was erratic due to inconsistent pressure control. Both issues combined to produce coils with inconsistent compaction and resultant potential damage to the coil.

Inconsistent Positioning

After analyzing the circuit and the power unit, the first issue of inconsistent positioning was determined to be a result of using large DIN cartridge valves, whose performance is susceptible to dirt and debris in the system. To match the filtration level of the hydraulic power unit, the team chose low leakage poppet style pilot operated check valves to replace the DIN valves. In order to meet the expected flow rate requirements two poppet PO checks were installed in parallel for each DIN valve.

Inconsistent Pressure Control

The issue of inconsistent pressure control was found to be caused by over pressurization of the system during initial cylinder approach. Specifically, the cylinders were run in regeneration mode for the initial approach and dropped out of regeneration mode for final compaction. However, due to system resistance the pressure required for regeneration mode was greater than that required for final compaction. Because control of pressure was being accomplished by a proportional pressure relief valve – lowering the pressure set point at the time of compaction resulted in periods of instability as the valve attempted to lower the system pressure to the desired level – adversely affecting compaction force.

Solution Achieved

The solution was achieved with the replacement of the existing valves with faster, larger Parker proportional directional and relief valves, along with a wholesale redesign of the manifold, simplification of the hydraulic circuitry, and enlargement of associated piping and hoses, which resulted in lowering regeneration system pressure to levels well below compaction pressure, greatly improving compaction reliability. Once the redesign was completed, the hydraulic control system was assembled, tested and packed for shipment to Shanghai, China.

^top

horizontal-compactor
Horizontal Compactor

vertical-compactor
Vertical Compactor

parts-gopher
Over $100 million of Parker
parts ready to ship.




Benji Grubel   When Failure is Not an Option...Fluid Monitoring is the Answer
Ray McCann
Sales Engineer

riccardo-ricci-sorensen-systems   Micro Hydro Can Be Real Big For Consumers
Riccardo Ricci
Sorensen Systems

peter-rhoten-hope-air-systems   A Flow Meter Can
Lower Operating Costs

Peter Rhoten
Hope Air Systems

doug-markham-ipower-new-england   Your VMI program may be compromised if the part numbers on the bin don't match
Doug Markham
President, iPower NE



         

Company Products Tech Support Resources
Parker-Distributor We are a full line
Parker Distributor
distranet-logo The DistraNet inventory is over $100 Million
ISO-9001:2008 Certified View ISO 9001:2008 Certificates
About Us
Contact Us
Disclaimers/Terms
Locations
Employment
Catalogs
Find a Part
Line Cards
Order Online
Product Lines
Air Leak Calculator
CAD Drawings
Condensate Calculator
Hose Finder App
Metric Sizing Guide
Technical Assistance
Ask the Owner
New Products Archive
Press Releases
Parker Hannifin